A Developers team created multiple changes but only some pass all checks. What should they do regarding the Sprint increment?
Answer
Do not include work that violates the Definition of Done; either fix it or keep it out of the increment
Explanation
Scrum requires that the increment meet the Definition of Done. If checks fail, the work is not done and must be corrected or excluded.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In Scrum, who is accountable for ensuring that the Product Backlog is visible, transparent, and understood?
View question →
During a Sprint, the Development Team discovers a new technical approach. What is the appropriate response in Scrum?
View question →
Which statement best describes the purpose of the Daily Scrum in Scrum?
View question →
How should a Developers team typically handle technical debt within the Scrum framework?
View question →
A team wants to improve the quality of results. Which PSD guideline most directly supports creating potentially releasable increments?
View question →
Assume a team’s Definition of Done includes automated tests and code review. Which outcome is most consistent with that Definition?
View question →