A Development Team discovers mid-sprint that a forecast is incorrect and they may not finish all selected Product Backlog items. What should they do first?
Answer
Inspect the situation with the team, adapt the plan toward the Sprint Goal, and update the Sprint Backlog as needed.
Explanation
Scrum expects adaptation based on inspection and empirical evidence. The team updates the Sprint Backlog to stay aligned with the Sprint Goal.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In Scrum, what best describes the relationship between a Sprint Goal and the Sprint Backlog?
View question →
Which is a valid reason for changing the Sprint Goal during a Sprint?
View question →
A Scrum Team has an Increment that meets the Definition of Done for the selected work, but the Product Owner finds defects still present. What does Scrum require?
View question →
During a Daily Scrum, a team member says, “I’ll update the backlog items after the sprint review tomorrow.” What is the most accurate Scrum interpretation?
View question →
What is the primary outcome of the Sprint Review?
View question →
Which statement best describes the purpose of Sprint Planning in Scrum?
View question →