A Development Team is halfway through a Sprint when they realize they cannot complete all Sprint Backlog items. What should they do?
Answer
Collaborate with the Product Owner to adjust the Sprint Backlog, ensuring the Sprint Goal is still met.
Explanation
The Development Team and Product Owner can negotiate the Sprint Backlog during the Sprint, but the Sprint Goal should remain unchanged. Extending the Sprint or removing items unilaterally is not allowed.