A Development Team is struggling to complete the Sprint Goal. What should they do?

Answer

Collaborate with the Product Owner to adjust the Sprint Backlog while keeping the Sprint Goal.

Explanation

The team can adjust the Sprint Backlog as long as the Sprint Goal remains achievable and valuable.