A Product Owner is refining the Product Backlog and wants to ensure the items are ready for the upcoming Sprint. Which of the following best describes the level of detail needed for Product Backlog items at the top of the backlog?
Answer
They should be small enough to be completed within one Sprint and have clear acceptance criteria.
Explanation
Product Backlog items at the top are typically refined to be small enough for a Sprint and include enough detail for the Developers to forecast them. They do not need task breakdowns or assignments before Sprint Planning.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
What is the primary way the Product Owner communicates the product vision and goals to the Scrum Team and stakeholders?
View question →
What is the primary purpose of the Product Goal?
View question →
Who is responsible for creating the Definition of Done if it is not an organizational standard?
View question →
What is the Product Owner's role in the Daily Scrum?
View question →
How should the Product Owner handle technical debt?
View question →
During a Sprint, the Developers inform the Product Owner that they have discovered additional work needed to meet the Sprint Goal. What should the Product Owner do?
View question →