A Product Owner is refining the Product Backlog and wants to ensure the items are ready for the upcoming Sprint. Which of the following best describes the level of detail needed for Product Backlog items at the top of the backlog?

Answer

They should be small enough to be completed within one Sprint and have clear acceptance criteria.

Explanation

Product Backlog items at the top are typically refined to be small enough for a Sprint and include enough detail for the Developers to forecast them. They do not need task breakdowns or assignments before Sprint Planning.