A Scrum Team completes a Sprint but learns mid-Sprint that a key dependency is unavailable and will slip. To maximize value and preserve transparency, what is the most appropriate Scrum action?

Answer

Reassess the plan using the Daily Scrum, update the forecast, and if necessary renegotiate the Sprint Backlog toward the Sprint Goal

Explanation

Scrum relies on continuous inspection and adaptation. The Daily Scrum is used to reassess and update the forecast; Sprint scope changes are allowed when they support the Sprint Goal.