A Scrum Team completes a Sprint but learns mid-Sprint that a key dependency is unavailable and will slip. To maximize value and preserve transparency, what is the most appropriate Scrum action?
Answer
Reassess the plan using the Daily Scrum, update the forecast, and if necessary renegotiate the Sprint Backlog toward the Sprint Goal
Explanation
Scrum relies on continuous inspection and adaptation. The Daily Scrum is used to reassess and update the forecast; Sprint scope changes are allowed when they support the Sprint Goal.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
A Product Owner repeatedly cancels refinement sessions because “we can think about it later,” resulting in unclear items and frequent renegotiations during Sprint execution. What is the most likely root cause from a Scrum perspective and the best targeted remedy?
View question →
A Developers’ estimate was intentionally inflated to gain stakeholder acceptance, but the team’s actual progress is lower. What is the most appropriate Scrum Master stance regarding trust and transparency?
View question →
In the scenario described, which statement best captures what the Scrum Master should do to improve compliance with the Scrum Guide while avoiding taking over the Developers’ decisions?
View question →
A Product Owner wants to add a new high-priority item mid-Sprint that may affect the Sprint Goal. What is the correct Scrum principle governing scope changes during the Sprint?
View question →
During Sprint Planning, the Scrum Master notices the Product Owner is still uncertain about ordering because many items are half-defined. What is the best intervention consistent with PSM I expectations?
View question →
Which interpretation aligns with how Scrum defines and uses empirical process control?
View question →