A Scrum Team decides to measure the “progress” of a Sprint by counting accepted user stories per day and uses this as the primary control metric. Which PSM I principle is being violated most directly?
Answer
Transparency and Inspection are violated by focusing on non-increment measures
Explanation
Using daily acceptance counts as the main progress signal can obscure true outcome-based progress toward a potentially releasable increment and undermines transparency of the actual work and product outcome.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
A Development Team uses a separate “quality checkpoint” outside the Sprint to approve work before it can be included in the increment. This checkpoint consistently delays feedback by several days. Which Scrum value or empirical principle is most threatened?
View question →
Which practice most strongly supports maintaining transparency and inspection when a team’s work depends on external services with variable response times during a Sprint?
View question →
Consider a scenario where a Scrum Team has multiple Products managed by one Product Owner and one shared Product Backlog. When a Sprint begins, the PO assigns items from different product areas based on last-minute priority changes. What best captures the resulting risk in Scrum terms?
View question →
During Sprint Planning, the Product Owner proposes a complex Product Backlog item that cannot be broken down into smaller work. The Development Team states it cannot commit to it and demands the PO remove it immediately. What is the most appropriate response consistent with PSM I?
View question →
A Product Owner tries to force a “pre-approved” increment definition by refusing any backlog item whose acceptance criteria were clarified during development. This results in frequent rework and the team routinely misses the Sprint Goal. What is the most likely Scrum-root cause?
View question →
A Development Team frequently declares “done” during the Sprint and demonstrates work immediately, but they do not integrate everything into a potentially usable Product Increment by the Sprint end. Which issue is most directly problematic?
View question →