A Scrum Team is new to Scrum and has not yet established a Definition of Done. What is the most appropriate action?
Answer
The Scrum Team should create a Definition of Done during Sprint Planning.
Explanation
The Scrum Team is responsible for creating the Definition of Done. If the organization has one, it must be used; otherwise, the team creates it during Sprint Planning.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
What is the recommended approach for scaling Scrum to multiple teams working on the same product?
View question →
A Scrum Team is in the middle of a Sprint when the Product Owner discovers that a newly identified feature could significantly increase product value. What is the most appropriate action?
View question →
Which of the following is true about the Sprint Review?
View question →
A Scrum Team is midway through a Sprint when the Product Owner learns that a competitor has released a feature that makes one of the current Sprint Backlog items obsolete. What is the most appropriate action?
View question →
During a Sprint Retrospective, the Scrum Team identifies that the Definition of Done is not being consistently applied. Who is responsible for updating the Definition of Done?
View question →
Which of the following best describes the purpose of the Sprint Backlog?
View question →