A Scrum Team notices that stakeholders increasingly request changes mid-Sprint that materially impact Sprint Goal achievement. What is the most appropriate Scrum-consistent response?
Answer
Record the change requests, and if they are not necessary for the Sprint Goal, defer them to the next Sprint while maximizing focus during the current Sprint.
Explanation
Scrum protects the Sprint Goal by discouraging scope changes during the Sprint; changes should be handled through the Product Backlog and subsequent Sprint planning when they can be incorporated.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In a Sprint Review, the team’s output is largely not demonstrated because it is “not ready,” but the Product Owner still claims progress. Which interpretation aligns best with Scrum?
View question →
Which scenario best illustrates the Scrum Master’s duty regarding event effectiveness when stakeholders request skipping Sprint Review to “save time,” arguing that production metrics suffice?
View question →
A Scrum Team’s Definition of Done is overly broad and allows merging incomplete work as long as “tests exist.” What is the most Scrum-accurate improvement path?
View question →
In a PSM I context, which statement best explains how Scrum’s empirical process control constrains the Development process when forecasts about delivery are unstable?
View question →
Multiple teams share a common Definition of Done but use different criteria for “ready.” In practice, integration fails frequently near Sprint end. What is the most advanced PSM I-aligned corrective action?
View question →
A Product Owner is repeatedly asked to prioritize during the Sprint, but the work is already committed toward the Sprint Goal. What is the most correct Scrum stance?
View question →