A stakeholder asks for a change to be included in the next Sprint immediately. What is the most appropriate PSPO I response?

Answer

Discuss it and, if desired, add or reorder the Product Backlog for future consideration

Explanation

In Scrum, changes are managed via the Product Backlog and its ordering; you do not re-plan the Sprint by directly changing the Sprint Backlog unless the Sprint is still adjustable per Scrum guidance. The best next step is updating the backlog for future work.