A stakeholder asks for a change to be included in the next Sprint immediately. What is the most appropriate PSPO I response?
Answer
Discuss it and, if desired, add or reorder the Product Backlog for future consideration
Explanation
In Scrum, changes are managed via the Product Backlog and its ordering; you do not re-plan the Sprint by directly changing the Sprint Backlog unless the Sprint is still adjustable per Scrum guidance. The best next step is updating the backlog for future work.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
Read the passage and answer the question based on it.
View question →
Read the passage and answer the question based on it.
View question →
Which statement about the Product Goal is correct?
View question →
A team consistently delivers stories, but customers report no noticeable improvement. What should the Product Owner most likely do next?
View question →
During refinement, the Product Owner wants to improve clarity and readiness. Which action is most consistent with refinement goals?
View question →
Which artifact is explicitly accountable to the Product Owner?
View question →