A stakeholder requests a new feature after a Sprint has started. What is the most accurate PSPO I approach?
Answer
Put it on the Product Backlog and consider it for future Sprints
Explanation
Work for the Sprint is selected during Sprint Planning; new items should be considered for later by updating the Product Backlog.