A student says that sprint length can be changed within a single Sprint to handle delays. Which response is correct?
Answer
No, the Sprint duration is fixed and should not be changed mid-Sprint.
Explanation
Once a Sprint starts, its duration remains fixed; the Sprint Goal may be updated only under specific circumstances.