A team forecasts a Sprint Backlog that may include work that is not fully understood yet. What is the best practice principle behind Scrum’s approach to this risk?

Answer

Use empirical process control: transparency, inspection, and adaptation as learning occurs

Explanation

Scrum is built on empiricism, using frequent inspection and adaptation rather than pretending uncertainty can be eliminated upfront.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error
QuestionBack to list