A team forecasts a Sprint Backlog that may include work that is not fully understood yet. What is the best practice principle behind Scrum’s approach to this risk?
Answer
Use empirical process control: transparency, inspection, and adaptation as learning occurs
Explanation
Scrum is built on empiricism, using frequent inspection and adaptation rather than pretending uncertainty can be eliminated upfront.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
Which statement correctly describes the purpose of the Daily Scrum?
View question →
During a Sprint, the Scrum Master sees the Developers preparing to change Sprint Goal commitments after a new request arrives. What is the most appropriate Scrum-aligned response?
View question →
The Product Owner claims that because stakeholders requested a new feature, the team should simply add it to the current Sprint without affecting anything else. Based on Scrum, what is the most accurate implication?
View question →
Which activity is most directly associated with the Product Owner’s responsibility for Product Backlog management?
View question →
In Scrum, which statement best captures the purpose of the Product Backlog?
View question →
What best explains why the Developers own the Sprint Backlog?
View question →