A team is debating whether an item should move from “In Progress” to “Done.” The team’s Definition of Done is: 'The feature is usable, meets acceptance criteria, passes automated tests, and is documented.' Which action is most appropriate?

Answer

Wait until it meets all parts of the Definition of Done, including usability and acceptance criteria

Explanation

Scrum requires using the Definition of Done consistently; an increment is only done when it satisfies every stated criterion.