During a Sprint, Developers request clarification on a user story. What should the Scrum Team do?

Answer

Collaborate with the Developers and use the Sprint Backlog and Product Backlog as the basis for clarification

Explanation

Within the Sprint, the team focuses on the Sprint Goal. Clarifications are handled collaboratively without changing the Sprint Goal or bypassing Product Owner stewardship of the Product Backlog.