During a Sprint, the Scrum Master notices that the Development Team is frequently interrupted by external stakeholders. What should the Scrum Master do?
Answer
Help the team and stakeholders understand that the team should not be interrupted during the Sprint.
Explanation
The Scrum Master serves the organization by helping stakeholders understand how to interact with the Scrum Team. The team should be protected from unnecessary interruptions during the Sprint.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
A Product Owner wants to change the Sprint Goal midway through the Sprint. What should the Scrum Team do?
View question →
Which of the following is a responsibility of the Development Team?
View question →
A Development Team member suggests a new technical approach that could improve quality but might slow down the current Sprint. What should the team do?
View question →
Which of the following is a key responsibility of the Product Owner during the Sprint?
View question →
What is the primary purpose of the Sprint Backlog?
View question →
Which statement about the Daily Scrum is true?
View question →