During a Sprint, the team discovers the scope is too large. What is the most Scrum-aligned response?
Answer
Reduce the Sprint scope and update the Sprint Backlog to stay on track
Explanation
Within a Sprint, the team can adjust the Sprint Backlog to ensure it can meet the Sprint Goal.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
Which statement best describes the function of the Daily Scrum?
View question →
A Development Team wants to start building the next Sprint’s increment before the Sprint Planning event ends. Which Scrum guidance best applies?
View question →
A team’s lead time increases after starting work on a new feature set. What PSD-focused practice best helps reduce the time from change to delivery?
View question →
Which outcome is most likely from a well-executed Sprint Retrospective?
View question →
In the Scrum Team, what is the primary responsibility of the Product Owner?
View question →
A Scrum Developer reports that they completed a story but did not run required automated tests. According to PSD practices, what is the best action?
View question →