During a Sprint, the team discovers the scope is too large. What is the most Scrum-aligned response?

Answer

Reduce the Sprint scope and update the Sprint Backlog to stay on track

Explanation

Within a Sprint, the team can adjust the Sprint Backlog to ensure it can meet the Sprint Goal.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error