During Sprint Planning, which combination most accurately explains what the Developers select and what they deliver?

Answer

Developers select Product Backlog items and plan how to deliver an increment that meets the Sprint Goal

Explanation

The outcome of Sprint Planning is the Sprint Goal plus the Sprint Backlog, which is formed by selecting items and creating a plan to deliver the increment toward the Sprint Goal.