In a scenario where two teams share a single Product Owner and Product Backlog, which practice is most aligned with Scrum’s requirements?

Answer

A single ordered Product Backlog exists, and each team contributes toward a Sprint Goal using work selected from that backlog

Explanation

Multiple teams may use one Product Backlog when they are organized to collaborate, but ordering remains a Product Owner responsibility. Independent reordering or duplicated backlogs conflict with Scrum’s backlog ownership.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

Passage: The Scrum Master observes that after Sprint Review feedback, the Product Owner produces a new roadmap and assigns work for the next sprint based on the roadmap’s expected scope. The team then stops refining the Product Backlog, claiming the roadmap items are now “locked.” During Sprint Planning, the Developers select items that exactly match the expected scope, even though early indicators during the sprint suggest that some items may be less valuable. The Sprint Goal ends up becoming a paraphrase of the roadmap’s deliverables rather than a concise objective for value.

View question →

A Development Team proposes adding new tasks mid-Sprint that change the definition of ‘Done’ after work has started. What is the best Scrum-consistent approach?

View question →

A team’s Daily Scrum has become a status meeting to report progress to external stakeholders. What is the most accurate implication?

View question →

In Scrum, which situation most strongly indicates the organization is still effectively treating the Product Backlog as a delivery plan rather than an ordered commitment?

View question →

Passage: During a sprint, the Product Owner receives new customer evidence suggesting that the next best value is now a different feature than the one selected at the start of the sprint. The Developers argue that they already committed to the Sprint Goal and therefore cannot change their work focus until the sprint ends. The Scrum Master notices that while the Product Backlog is ordered for value, the team is also using the sprint as a “frozen plan” to avoid churn. At the Daily Scrum, progress is discussed only against the original selected items, not against the Sprint Goal.

View question →

Which statement best captures the relationship between Sprint Backlog, work plan, and the empirical inspection loop?

View question →

QuestionBack to list