In PSD, what is the most appropriate way to handle a change discovered mid-sprint (e.g., new acceptance criteria)?
Answer
Update the product backlog and collaborate with the Product Owner during the sprint
Explanation
PSD aligns with Scrum principles: changes affect the plan, and the team collaborates with the Product Owner to adjust backlog and work as appropriate.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In Professional Scrum Developer (PSD), what is the primary purpose of the Definition of Done?
View question →
Which statement best reflects the PSD view of technical debt?
View question →
A Development Team repeatedly exceeds the sprint scope because small changes keep accumulating. What is the most PSD-aligned response?
View question →
Consider the following actions: (1) add automated tests, (2) reduce build times, (3) refactor the module that frequently changes, and (4) improve monitoring. Which are most aligned with PSD continuous improvement of the development environment and quality?
View question →
Which combination best describes a key PSD practice related to software quality and learning?
View question →
Read the text and choose the best interpretation of its implications for PSD teamwork.
View question →