In Scrum, who is responsible for canceling a Sprint if it no longer makes sense?

Answer

Product Owner, based on the Sprint Goal

Explanation

The Product Owner has the responsibility to decide whether the Sprint should be canceled. The decision is tied to whether the Sprint Goal still makes sense.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

A developer claims they can safely skip code reviews because the team has a strong backlog. Which alternative is more aligned with PSD practices?

View question →

A team uses a shared codebase where build failures occur once a day. Which practice most directly supports a “fast feedback loop” in PSD?

View question →

What is the primary purpose of the Sprint Review for the Scrum Team?

View question →

Which outcome best demonstrates “no surplus work” during a Sprint under Scrum?

View question →

Which statement best describes the purpose of the Definition of Done (DoD)?

View question →

A Development Team frequently changes its plan after each daily stand-up. Which action most improves predictability without breaking Scrum?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds