What is the most accurate relationship between “Product Backlog Items” and an “increment” delivered during Sprints?
Answer
An increment is the outcome of selected PBIs that meet Definition of Done
Explanation
Each Sprint increment comes from selected PBIs and must satisfy the Definition of Done to be considered usable.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
What does “self-management” mean for Developers in Scrum?
View question →
Which scenario is most consistent with the Scrum Developer obligation to ensure quality?
View question →
Which statement best describes the primary goal of a Sprint in Scrum?
View question →
During a Sprint, a Developer learns that a previously selected plan for a PBIs implementation is no longer suitable. What is the best action consistent with Scrum?
View question →
A Developers’ effectiveness depends on how they handle shared work and dependencies. Which action best reflects PSD teamwork and collaboration?
View question →
A team is concerned that improvements made during the Sprint might be forgotten later. What PSD guidance best addresses this?
View question →