What is the Scrum Master’s primary accountability regarding the event of a Daily Scrum?
Answer
Ensure the event happens and remains focused on the plan for the next 24 hours
Explanation
The Scrum Master enables the team to use the Daily Scrum effectively, while the Development Team conducts the event. The focus is on progress toward the Sprint Goal.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
What does the Product Owner do during Sprint execution regarding the ordering of the Product Backlog?
View question →
A Scrum Team is continuously adding items to the Sprint Backlog after work has started, without changing the Sprint Goal. What is the most likely issue?
View question →
Which artifacts must exist in Scrum, according to PSM I?
View question →
Which statement best describes the main purpose of the Product Backlog in Scrum?
View question →
At the Sprint Review, who primarily presents and discusses the Increment?
View question →
Which is the best description of the Sprint Goal?
View question →