What is the Scrum Master’s primary accountability regarding the event of a Daily Scrum?

Answer

Ensure the event happens and remains focused on the plan for the next 24 hours

Explanation

The Scrum Master enables the team to use the Daily Scrum effectively, while the Development Team conducts the event. The focus is on progress toward the Sprint Goal.