What is the time-box for the Sprint Planning meeting for a one-month Sprint?
Answer
8 hours
Explanation
Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team