What is the time-box for the Sprint Planning meeting for a one-month Sprint?

Answer

8 hours

Explanation

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

Who can cancel a Sprint?

View question →

What is the recommended duration for a Sprint Retrospective for a one-month Sprint?

View question →

Which of the following best describes the Scrum Master's role?

View question →

Who is responsible for ensuring that the Scrum Team adheres to Scrum theory, practices, and rules?

View question →

What is the primary output of the Sprint Planning meeting?

View question →

Which of the following is NOT a Scrum event?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds