Which artifact contains the work planned for the Sprint?

Answer

Sprint Backlog

Explanation

The Sprint Backlog is the set of items selected for the Sprint plus the plan for delivering the Increment.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

What does the Product Owner primarily do regarding the Product Backlog?

View question →

Which statement about the Daily Scrum is correct?

View question →

In Scrum, what is the purpose of the Product Backlog?

View question →

During which event is progress toward the Sprint Goal inspected and adapted?

View question →

What is the primary purpose of the Sprint Review?

View question →

Which statement best describes a Scrum Team?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds