Which artifact represents the plan the Developers will use to deliver the Sprint Goal?

Answer

Sprint Backlog

Explanation

The Sprint Backlog is the Developers’ plan for how they will meet the Sprint Goal.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

Which is an example of a good PSD practice for maintaining quality?

View question →

What does “Definition of Done” (DoD) help the team do?

View question →

In Scrum, who is responsible for deciding the scope of work in a Sprint (the Sprint Goal)?

View question →

What should happen at a Sprint Review?

View question →

In PSD practice, why is producing a working Increment important?

View question →

Which statement best describes the Developers’ role in Scrum according to PSD ideas?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds