FirstInTest
QuestionsFlash card
CoursesVideosPricingNewsBlogFeedback
Questions/Agile Certifications

Which metric is commonly associated with Scrum transparency of delivery and forecasting?

Answer

Velocity

Explanation

Velocity is often used as a forecasting aid based on past performance. It helps the team plan but is not a goal in Scrum.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

A team is trying to improve how they work together. They are practicing Scrum values daily and using the Scrum events to learn and adjust. The Product Owner clarifies what matters most for the product, and the Developers focus on delivering an increment that meets the Definition of Done. The team also holds a Daily Scrum to inspect progress toward the Sprint Goal and update their next steps. After the sprint, they review what they learned and adapt the next plan based on feedback and new information.

View question →

During the Daily Scrum, what is the purpose of the event?

View question →

What does “increment” mean in Scrum?

View question →

What is a Sprint in Scrum?

View question →

Which event in Scrum is primarily used to inspect progress and adapt the plan?

View question →

In Scrum, what is the outcome of the Sprint Planning event?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds