Which outcome is most closely associated with the Daily Scrum in PSD?
Answer
Inspecting progress toward the Sprint Goal and adapting the plan
Explanation
The Daily Scrum is for inspection and adaptation toward the Sprint Goal, helping the Developers adjust their plan for the next 24 hours.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In PSD, what is the purpose of the Sprint Backlog?
View question →
What is a key responsibility of the Product Owner related to refinement and the Product Backlog?
View question →
Scenario-based: A stakeholder asks for an additional feature during the Sprint. What is the most PSD-consistent response?
View question →
A team frequently finds work late in the Sprint. Which PSD practice most directly helps reduce this risk?
View question →
What is the most accurate interpretation of “Increment” in PSD?
View question →
A team’s quality issues repeatedly appear during testing at the end of the Sprint. Which PSD principle is most directly being violated?
View question →