Which situation most likely indicates that a Sprint might need to be canceled?
Answer
The Sprint Goal becomes obsolete due to changes that make it irrelevant
Explanation
Scrum allows cancelation when the Sprint Goal is no longer achievable or has become obsolete. Minor delays alone do not justify canceling.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
During a Daily Scrum, what is the primary purpose for the Developers?
View question →
A team uses a “Definition of Done” that applies only to coding, not testing or documentation. What risk does this create and what is the best Scrum-aligned remedy?
View question →
Which artifacts are used to maximize transparency of key information in Scrum?
View question →
A Scrum Master hears that the team wants to skip the Sprint Review because stakeholders are busy. A stakeholder asks for evidence of progress and outcomes anyway. What is the most Scrum-consistent response?
View question →
A team is working on the same Sprint Backlog item for three days with no measurable progress. What is the best Scrum-aligned action?
View question →
In Scrum, which statement best describes how the Sprint Goal relates to the work of the Developers?
View question →