Q8. Mr. Armaan is appointed as quality control manager in a factory. The list of steps to monitor the performance is shared with him. Mr. Armaan is asked to put the following steps in correct order. A. Employees must be trained to meet the target. B. Comparing the criteria set with the report of the personal observation. C. Setting the criteria against which actual performance would be measured. D. Keeping in mind the key result area, the deviation which go beyond the permissible limit is to brought to notice. E. Personally observe the work done by workers. Choose the collect answer from the options given below:

Answer

C, E, B, D, A

Explanation

The correct sequence of steps in monitoring performance (controlling process) is:C. Setting the criteria against which actual performance would be measured.E. Personally observe the work done by workers (or measuring actual performance).B. Comparing the criteria set with the report of the personal observation.D. Keeping in mind the key result area, the deviation which go beyond the permissible limit is to brought to notice (analyzing deviations).A. Employees must be trained to meet the target (taking corrective action).

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error
QuestionBack to list