A project’s cost performance is deteriorating due to underestimated labor hours early in the timeline. Which metric best diagnoses whether the project is spending more than planned for the work actually achieved?

Answer

Cost Performance Index (CPI)

Explanation

CPI directly compares earned value to actual cost, indicating whether costs are exceeding what the achieved work warranted.