A project’s schedule is trending late despite on-time sprint completions. Which principle best explains why this may still indicate a schedule performance issue requiring corrective planning?

Answer

Schedule variance must consider critical path dependencies and not only local iteration milestones.

Explanation

Even with on-time iteration outputs, dependencies (critical path) can make the overall schedule slip. Schedule performance requires holistic measurement against planned baselines and path impacts.