A project’s schedule is trending late despite on-time sprint completions. Which principle best explains why this may still indicate a schedule performance issue requiring corrective planning?
Answer
Schedule variance must consider critical path dependencies and not only local iteration milestones.
Explanation
Even with on-time iteration outputs, dependencies (critical path) can make the overall schedule slip. Schedule performance requires holistic measurement against planned baselines and path impacts.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
The project manager must decide whether a change request is “beneficial” when it improves a single KPI but increases cost and delays a dependent milestone. Which analysis approach is most consistent with integrated change control?
View question →
In the described rollout, which action best aligns with managing stakeholder engagement while addressing a risk that could derail scope stability?
View question →
A vendor claims its backlog items are “unblocked,” but internal acceptance is failing due to missing evidence artifacts. Which corrective approach best represents effective procurement and vendor management coordination?
View question →
During execution, the project’s risk register is updated after new information appears, but some mitigations remain stale because owners haven’t been notified. Based on the scenario, what is the most accurate explanation of why this is failing?
View question →
A team escalates a barrier: the architecture decision is unclear, causing duplicated work. Which response most directly follows the project communication and team alignment intent while minimizing rework?
View question →
A stakeholder group is passive at first but suddenly becomes highly influential after seeing a live demo. What is the most effective immediate move to prevent unmanaged expectations from becoming scope creep?
View question →