A Product Owner receives conflicting feedback from two customer groups about feature priority. Which action best supports an empirical approach?
Answer
Use evidence such as impact, risk, and validated learning to reorder
Explanation
Empiricism favors using available evidence to make trade-offs. The Product Owner orders the backlog to maximize value under uncertainty, not merely by votes or full consensus.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In Scrum, which are acceptable ways for the Product Owner to increase product value?
View question →
During a sprint, the Development Team identifies a new opportunity that could be addressed without reducing the Sprint Goal. Who decides whether to include it?
View question →
A team consistently finishes items but customers report the product does not solve their real problem. What is most likely the issue in Scrum terms?
View question →
Which example best illustrates the Product Owner’s role in ensuring transparency of value?
View question →
After a product increment is delivered, the Product Owner wants to incorporate learning from actual usage into future work. What is an effective next step?
View question →
Select the set of statements that are consistent with Product Owner accountability for acceptance of work.
View question →