In Scrum, which are acceptable ways for the Product Owner to increase product value?

Answer

Prioritize the Product Backlog to reflect value and risk

Explanation

The Product Owner is accountable for ordering the Product Backlog so it optimizes value. Pushing speed or overcommitting is not an accepted PO method for value maximization.