A Scrum Team is new and struggling to complete its work within the Sprint. What is the most appropriate action for the Scrum Master?
Answer
Coach the team on Scrum principles and help them improve their self-management.
Explanation
The Scrum Master serves the Scrum Team by coaching them in self-management and cross-functionality. The Scrum Master does not do the team's work or change Scrum rules.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
A Product Owner wants to change the Sprint Goal midway through the Sprint. What should the Scrum Team do?
View question →
Which of the following is a responsibility of the Development Team?
View question →
A Development Team member suggests a new technical approach that could improve quality but might slow down the current Sprint. What should the team do?
View question →
Which of the following is a key responsibility of the Product Owner during the Sprint?
View question →
What is the primary purpose of the Sprint Backlog?
View question →
During a Sprint, the Scrum Master notices that the Development Team is frequently interrupted by external stakeholders. What should the Scrum Master do?
View question →