A Scrum Team is tempted to merge the Daily Scrum with the Sprint Review to reduce meetings. What is the most correct conclusion?
Answer
It conflicts with Scrum because the Daily Scrum and Sprint Review have distinct purposes and cadence.
Explanation
Daily Scrum is for inspecting progress toward the Sprint Goal and adjusting the plan for the next 24 hours. Sprint Review is for inspecting the increment and adapting the Product Backlog, so merging them would mix purposes.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
During Sprint Planning, stakeholders request an additional outcome not present in the selected Sprint Backlog. The Developers refuse to commit. What is the strongest Scrum rationale?
View question →
A Product Owner states that for compliance reasons only the Scrum Master may decide which items are 'ready' for the next Sprint. What should the Developers conclude?
View question →
A Product Owner wants to change a high-impact requirement during a Sprint, claiming it will not affect scope because it is 'just one story.' Which PSM I interpretation is most accurate?
View question →
The Product Owner repeatedly postpones ordering updates because the organization wants 'forecast stability.' In the same timebox, the Developers claim they are blocked by newly discovered work and ask the PO to reprioritize. What is the most accurate PSM I assessment?
View question →
The Scrum Master notices that the Developers rarely update the Sprint Backlog during the Sprint, and they keep the same tasks even after they learn something new. The PO also says this is fine because 'scope is fixed.' What is the core Scrum problem?
View question →
The Developers report that ordering Product Backlog items by 'business priority' is ineffective because dependencies are driving work sequencing. What is the best guidance?
View question →