The Developers report that ordering Product Backlog items by 'business priority' is ineffective because dependencies are driving work sequencing. What is the best guidance?

Answer

The Developers can decide sequencing within the Sprint, but the Product Owner remains responsible for Product Backlog ordering.

Explanation

The Product Owner orders the Product Backlog, but Developers are free to select how to turn ordered items into a usable increment. Sequencing decisions can consider dependencies without transferring ownership of ordering.