The Developers report that ordering Product Backlog items by 'business priority' is ineffective because dependencies are driving work sequencing. What is the best guidance?
Answer
The Developers can decide sequencing within the Sprint, but the Product Owner remains responsible for Product Backlog ordering.
Explanation
The Product Owner orders the Product Backlog, but Developers are free to select how to turn ordered items into a usable increment. Sequencing decisions can consider dependencies without transferring ownership of ordering.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
A Scrum Team is tempted to merge the Daily Scrum with the Sprint Review to reduce meetings. What is the most correct conclusion?
View question →
During Sprint Planning, stakeholders request an additional outcome not present in the selected Sprint Backlog. The Developers refuse to commit. What is the strongest Scrum rationale?
View question →
A Product Owner states that for compliance reasons only the Scrum Master may decide which items are 'ready' for the next Sprint. What should the Developers conclude?
View question →
A Product Owner wants to change a high-impact requirement during a Sprint, claiming it will not affect scope because it is 'just one story.' Which PSM I interpretation is most accurate?
View question →
The Product Owner repeatedly postpones ordering updates because the organization wants 'forecast stability.' In the same timebox, the Developers claim they are blocked by newly discovered work and ask the PO to reprioritize. What is the most accurate PSM I assessment?
View question →
The Scrum Master notices that the Developers rarely update the Sprint Backlog during the Sprint, and they keep the same tasks even after they learn something new. The PO also says this is fine because 'scope is fixed.' What is the core Scrum problem?
View question →