A team has not delivered a usable Increment at the end of the Sprint. What does Scrum require?

Answer

An Increment must meet the Definition of Done; otherwise it is not an Increment

Explanation

Only work that satisfies the Definition of Done is considered an Increment; otherwise it does not count as an Increment.