During a Sprint, new work is requested that seems valuable. What is the typical Scrum guidance?
Answer
The Development Team can adjust the Sprint Backlog as long as it keeps the Sprint Goal
Explanation
The Development Team manages the Sprint Backlog to deliver the Sprint Goal; changes can happen, but the Sprint Goal should remain intact.