During a complex integration project, the Developers choose to split a single Product Backlog item across multiple Increments. After the first Increment, they notice latent defects that make future parts impossible without rework. What is the best Scrum response?

Answer

Inspect the increment against the Definition of Done; if not done, it cannot be part of the increment.

Explanation

An increment must meet the Definition of Done to be released at the end of the Sprint. Latent defects indicate the item may not have met DoD, requiring inspection and adjustment.