During a Sprint Review, the Product Owner proposes a new feature that was not in the Sprint Backlog. What should the Scrum Team do?

Answer

Add it to the Product Backlog for consideration in future Sprints

Explanation

New ideas from the Sprint Review are added to the Product Backlog and prioritized for future Sprints, not inserted into the current Sprint.