During Sprint Planning, which decision is the Development Team primarily responsible for?
Answer
Estimating the effort for the selected Product Backlog items, Selecting the items for the Sprint Backlog and creating the plan
Explanation
The Development Team forecasts and translates selected backlog items into a plan by choosing how they will deliver the Increment.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
A stakeholder requests a new feature after a Sprint has started. What is the most accurate PSPO I approach?
View question →
Which is the best example of ensuring Product Backlog items are understood?
View question →
What is the Product Owner’s responsibility regarding acceptance of the Increment?
View question →
A team’s backlog contains items with unclear outcomes and no measurable value. What should the Product Owner do first?
View question →
How does the Product Owner relate to the concept of 'value' in Scrum?
View question →
When should the Product Owner update or refine backlog items?
View question →