During Sprint Planning, who is responsible for deciding how many Product Backlog items the Development Team can complete in the upcoming Sprint?
Answer
The Development Team, in collaboration with the Product Owner.
Explanation
The Development Team forecasts the work it can complete in the Sprint. The Product Owner helps by clarifying the Product Backlog and discussing the Sprint Goal.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
A Product Owner wants to change the Sprint Goal midway through the Sprint. What should the Scrum Team do?
View question →
Which of the following is a responsibility of the Development Team?
View question →
A Development Team member suggests a new technical approach that could improve quality but might slow down the current Sprint. What should the team do?
View question →
Which of the following is a key responsibility of the Product Owner during the Sprint?
View question →
What is the primary purpose of the Sprint Backlog?
View question →
During a Sprint, the Scrum Master notices that the Development Team is frequently interrupted by external stakeholders. What should the Scrum Master do?
View question →