During the Sprint Review, who primarily presents the Sprint outcome?
Answer
The Product Owner and Scrum Team together
Explanation
The Scrum Team (including the Developers) presents the Sprint’s results, while the Product Owner explains product progress and both work with stakeholders to review outcomes.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team