In Scrum, what is the most appropriate way for the Development Team to handle an urgent change requested by stakeholders mid-Sprint?
Answer
Wait until the next Sprint and use it to update the Product Backlog
Explanation
Scrum promotes commitment to the Sprint Goal; changes are typically handled through the Product Backlog and next Sprint. The Development Team may adapt tactics if needed, but the Sprint scope/goal should not be changed for every request.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
What does the Product Owner do during Sprint execution regarding the ordering of the Product Backlog?
View question →
A Scrum Team is continuously adding items to the Sprint Backlog after work has started, without changing the Sprint Goal. What is the most likely issue?
View question →
Which artifacts must exist in Scrum, according to PSM I?
View question →
Which statement best describes the main purpose of the Product Backlog in Scrum?
View question →
At the Sprint Review, who primarily presents and discusses the Increment?
View question →
What is the Scrum Master’s primary accountability regarding the event of a Daily Scrum?
View question →