Which statement best describes the relationship between the Sprint Goal and the Sprint Backlog?
Answer
The Sprint Goal is a fixed objective, and the Sprint Backlog is the set of items selected to achieve it
Explanation
The Sprint Goal provides a single objective for the Sprint, while the Sprint Backlog is the plan to meet that goal and can be adjusted as more is learned.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In Scrum, who is responsible for the creation of the Increment?
View question →
A Development Team is struggling to complete the Sprint Goal. What should they do?
View question →
What is the primary responsibility of the Scrum Master during the Sprint Planning?
View question →
A Scrum Team is considering skipping the Sprint Retrospective because they are behind schedule. What is the best advice?
View question →
A Scrum Team is distributed across multiple locations. What is the most effective way to handle the Daily Scrum?
View question →
Which of the following best describes the relationship between the Product Backlog and the Sprint Backlog?
View question →