A project manager inherits a portfolio with unclear success metrics. The sponsor demands “more dashboard reports” rather than business outcomes. Which approach best realigns scope and measures to business value while avoiding scope creep?

Answer

Facilitate a measurable outcomes workshop to define KPIs, then map deliverables to KPIs and update the project charter

Explanation

Defining measurable KPIs and mapping deliverables to business outcomes tightens scope and acceptance criteria, reducing ambiguity that drives unnecessary reporting changes. Updating the charter formalizes alignment early.