During execution, a team repeatedly violates sprint commitments due to hidden dependencies with another department. What is the most effective next action to address this risk and improve predictability?

Answer

Coordinate a dependency schedule with the other department and revise the plan based on real constraints

Explanation

Hidden dependencies are a risk driver; coordinating schedules and updating the planning artifacts based on actual constraints improves realism and commitment reliability.