A team uses a project plan that specifies dependencies incorrectly, causing critical delays in testing. Which sequence most accurately follows risk and dependency reasoning from the certificate’s project planning concepts?

Answer

Identify and document dependencies/assumptions, estimate impact, then monitor and update risk responses as information changes

Explanation

Correct dependency documentation and continual risk monitoring align with disciplined planning and iterative control, allowing schedules to reflect true relationships.