After Sprint Review, a stakeholder asks for more scope, but the team completed the Sprint Goal and wants to keep the work stable. What is the most Scrum-consistent response?
Answer
Agree to adjust the Product Backlog and plan in the next Sprint
Explanation
Scope changes are handled through the Product Backlog; the next Sprint can include adjusted priorities. A current Sprint should not be disrupted just to accommodate new requests.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
Which change most directly helps the Product Backlog remain transparent and useful according to the scenario?
View question →
What is the most accurate statement about the Sprint Goal?
View question →
A Product Backlog item is estimated and then later understanding changes. Which principle best explains what should happen next?
View question →
In the scenario, what is the Scrum value most directly challenged when the team members avoid surfacing impediments?
View question →
If the team discovers mid-sprint that a key dependency may slip, what is the best immediate action consistent with Scrum guidance?
View question →
In Scrum, what is the best interpretation of “Done”?
View question →